PHARE programme: decentralized system 1990-1995. Special report 3/97 Court of Auditors
1997/2056(COS)
OBJECTIVE: The Court of Auditors' special report concerns the management of the Phare
Programme from 1990 to 1995. The Court particularly criticizes the Decentralized Implementation
System (DIS) set up by the Commission, which over the years has come to occupy too dominant
a position in the implementation of Phare and the management of its appropriations.
At the same time, the Court makes a series of recommendations to the Commission with the aim
of securing improvements in the decentralized management of the funds allocated in future.
SUBSTANCE:
1) The Court's main criticism concerns the Decentralized Implementation System for the
implementation and management of the Phare programme of assistance to the countries of Central
and Eastern Europe. The Commission had set up the DIS with the aim of ensuring that programmes
ran smoothly and funding could be channelled more quickly.
In practical terms this meant that the Commission had partially delegated its supervisory and
monitoring role to its delegations on the spot and that technical and financial responsibilities were
largely assumed by the beneficiaries themselves.
The Court of Auditors also criticizes the fact that one of the Commission's prime preoccupations
has always been to ensure that the whole of the annual budget is committed, while contracting and
actual disbursement of funds did not proceed at the same pace, for a number of reasons:
-staffing limitations,
-lack of absorption capacity for the appropriations in the recipient countries,
-dispersal of funds among too many projects, etc.
The Court found that the decentralized procedures introduced by the Commission, which in
principle were supposed to facilitate the implementation of projects, had actually slowed down
rather than accelerating the award of contracts.
At the end of 1995, for instance, of the ECU 1294 m paid in advances and channelled through the
DIS, 38% (ECU 497 m) remained on deposit in the accounts of the national administrations of the
recipient countries. It may be recalled that between 1990 and June 1996 the Commission committed
ECU 5757 m under Phare (ECU 6700 m has been allocated for 1996 to 1999).
Meanwhile the decentralization of project management to national administration level was not
accompanied by the transfer of sufficient responsibilities from the Commission's central services
to its delegations on the spot (which, in any case, would not have sufficient staff and financial
expertise).
2) The programme management units (PMUs) responsible for managing Phare funds within the
national administrations of the recipient countries are also short-staffed and lack training (the Court
considers that the Commission should have provided training, at least in part).
Although the Commission contributed financially to the staff and operating costs of PMUs, it did
not formulate principles for this financing, or concerning how it should be accounted for and
audited. The Court also confirms that the intensive use of technical assistance to provide
administrative and operational support to PMUs (financed by Phare) has been costly, particularly
because of the limited competition involved in contracting (which often lacked transparency).
Some consultancies were awarded a disproportionate number of contracts. The Commission was
slow to set up a system for monitoring the expenditure of PMUs, and did not carry out an
appropriate evaluation of the programmes implemented.
3) Another important criticism concerns the way in which the Commission applied the rules on the
awarding of contracts. Around 80% of Phare funds under decentralized management are spent on
contracts for services (technical assistance), supplies or works. The award procedures are governed
by Article 118 of the Financial Regulation and Article 7 of the Phare Regulation. The Financial
Regulation lays down that these contracts are to be awarded 'after restricted invitations to tender'.
Article 7 of the Phare Regulation, on the other hand, stipulates that in the case of assistance
exceeding ECU 50 000 participation in invitations to tender and contracts shall be open on equal
terms to all natural and legal persons of the Member States and of the Phare countries. The Court
deplores the fact that the Commission clearly gave precedence to Article 118 of the Financial
Regulation by deciding that services contracts exceeding ECU 50 000 should be subject to restricted
invitations to tender. As a result, the principle of equal access for all was not always respected (the
revision of Article 118 of the Financial Regulation at the end of 1995 so as to require the prior
public announcement of all tenders in the Official Journal improved the transparency of the
conditions for awarding contracts under the DIS).
The Court's examination of some of the short-lists in 1993 and 1994 showed that enterprises based
in Member States secured contracts far more often than those from other countries. The frequency
with which companies were placed on short-lists was also lacking in balance: a mere 24 companies
(representing around 3% of the companies invited to tender) were consulted between 10 and 31
times more often than the rest. The evaluation of the tenders themselves also lacked transparency.
Generally speaking, and in conclusion, the Court of Auditors endorses the principle of decentralized
management, but considers it vital to rationalize its implementation by improving the definition of
tasks and reducing the number of programmes. Tasks of supervision and monitoring should, in
particular, be entrusted to the Commission's delegations on the spot. To this end, human resources
need to be increased.
Recipient countries should be more involved in the financing of the programmes, and the evaluation
of the projects carried out should be systematized and improved. �